Kilcohan Park Greyhound Stadium

In May 2008, CTS were contracted to this popular venue, which required the provision of extensive electrical installations to complete renovations inclusive of a bar, restaurant, offices and toilet facilities. The project had a completion time of 20 weeks.

The electrical overhaul of the entire building involved the provision of general services, new distribution boards, sockets, CAT 5E structured cabling and a PA system. Specialist lighting was required, together with general, emergency and external lighting to a carpark and access points. Security features included the installation of CCTV, access control, intruder alarm and fire alarm systems.