EY Phase 2

CTS Group were delighted to have been engaged to complete a 4,500 sq. ft. fit out for EY's new office extension.

 

In this phase, a new office was completed with LED efficient lighting panels and a full CAT. 6 certified data installation which included an intruder alarm, a fire alarm, CCTV, sockets, general and emergency lighting, wiring to air conditioning units and under floor power distribution and desk module power systems. This project was completed within 6 weeks.